2014 - Sishen Solar Farm
• Assistant Site Manager Civil/Mechanicle Engineer for Arciona
•470 trackers
• 39 inverter stations
• 160 000 solar panels totaling up 80 MW.
Site Manager - Transport - Cranes - Installation •Pre-planning and start-up • The planning and scheduling for erection of the wind turbines
•The daily planning of work schedules and labour/supervision management on site. •Logistical planning for of loading of ships and the delivery schedules.
2013 Hopefield Windfarm project
Contract Senior Site Supervisor: Minor Civil Works including: • Additions to cable trenches and circuit breakers •Emergency overflow dam
• Pipe work and concrete canal
2012- 2013 Eskom: Omega Sub Station
Contract Senior Site Supervisor •Responsible for all civils to towers •Assembly and erection of towers •Stringing & Regulation of line
• OPGW & Earth wire
2012 - 2013 Eskom: Koeberg-Muldersvlei Turn-In 400kv line.